construction waste sorting process
Capacity:150-200 Cubic Meter Per Day
Working hour: 10-12 hours per day
Crushing and screening concrete blocks, waste bricks, stones and the like to recycle resources.
After construction waste like stone pieces is transported to Guoxin construction waste comprehensive treatment line.
The transport vehicle will dump it to vibrating feeder for uniform feeding and preliminary screening.The waste of large size will be put into the jaw crusher for crushing.
Exposed to muck bolter for screening and magnetic separation in de-ironing separator.
After initial crushing, muck screening and iron removal
The construction waste will be conveyed to positive pressure lightweight mateirals separator to separate most lightweight waste from other waste. And transported to manual pickup table station.
The mixture stored in the silo temporarily is conveyed to the horizontal counter-attack crusher for disposal.
Being carried to the horizontal counter-attack crusher by belt conveyor, it will receive the secondary magnetic separation and screening by horizontal screen. The screened mixture is transported to the three-level screening machine-horizontal screen.